Short answer
Dig a strip foundation at least 300mm deep and twice the wall width, cast it level in concrete, then lay bricks or blocks in a proper bond on a 10mm mortar bed with staggered perpends. Cap it with a coping that oversails both faces and includes a drip.
A low garden wall is one of the more satisfying DIY jobs and one of the easier ones to get structurally wrong. Almost all failures come from a foundation that was too shallow, a mortar that was too strong, or the absence of a coping to keep water out of the top.
Safety
What you'll need
- Bricks or blocks, plus 5% for cuts and breakages
- Concrete for the foundation — C20 mix or ready-mixed
- Building sand and cement, plus plasticiser or lime
- Coping stones or bricks on edge
- A brick trowel, spirit level, line and pins, and a gauge rod
Step by step
- Check what the wall must do and how high it will be.Free-standing, on level ground, under 600mm and away from a highway is straightforward DIY. Anything retaining soil, taller than about 1m, or where a collapse could hit a person or a road needs designing.
- Dig the foundation trench.At least twice the wall width, and at least 300mm deep for a low wall — deeper on clay or where the ground is soft, down to firm undisturbed subsoil. Below the frost line, which in the UK is normally taken as 450mm in exposed areas.
- Cast the foundation level.A C20 concrete mix, at least 150mm thick, tamped and levelled. Get it flat — every millimetre of error in the foundation has to be made up in the first mortar bed.
- Let it cure and set out the first course dry.24-48 hours before building on it. Lay the first course out dry with the joints spaced to check the wall length works in whole bricks before mixing any mortar.
- Mix the mortar to the right strength.For a garden wall in normal exposure, 1 part cement to 5 or 6 parts building sand with a plasticiser, or a lime-based mix on an older or softer brick. A stronger mix is not a better mix — it cracks the bricks instead of the joints.
- Lay to a line and check every course.Build the ends up first, run a line between them, and lay to it. Check level along and across, and plumb at the ends, on every course. A gauge rod marked with the course heights keeps everything consistent.
- Use a proper bond.Stretcher bond for a half-brick wall, English or Flemish garden wall bond for a one-brick wall. Perpends must be staggered — vertical joints lining up is a straight structural weakness.
- Include a damp-proof course and movement joints.A DPC at the base, at least 150mm above ground, stops rising damp making the wall spall in frost. On runs over about 6m, include a vertical movement joint.
- Point the joints as you go.When the mortar is thumbprint-hard, strike the joints — bucket-handle or weather-struck sheds water best on an exposed wall. Recessed joints look good and hold water, which is a problem outdoors.
- Fit a coping with a drip.Coping stones or bricks on edge, bedded in mortar, oversailing both faces by at least 25mm with a drip groove underneath. Water getting into the top of a wall is what destroys garden walls.
Tips
- Build in cool damp weather rather than hot sun. Mortar that dries before it cures has almost no strength.
- Cover new work with plastic overnight if frost is forecast. Frost on green mortar ruins it and it will not recover.
- Keep the bricks under cover before laying. Saturated bricks float on the mortar and will not stay where you put them.
Common mistakes
- Using a strong 1:3 mortar mix — Mortar should be weaker than the brick, so that movement cracks the joint rather than the brick. A too-strong mix transfers stress into the bricks and spalls their faces.
- Leaving the top of the wall uncapped — Water enters the open top, saturates the wall and freezes. Uncapped garden walls fail from the top down within a few winters. A coping with a drip is not decoration.
If it doesn't work
Wall cracking vertically at a regular spacing
Cause: Thermal and moisture movement with no movement joint — Fix: Cut in a vertical movement joint and fill it with a flexible sealant. Long walls need one every 6m or so.
Bricks spalling on the face
Cause: Water and frost, often with too strong a mortar or no coping — Fix: Cap the wall and repoint with a weaker mix. Badly spalled bricks need cutting out and replacing.
Wall settled and cracked at one end
Cause: Foundation too shallow or on soft ground — Fix: There is no cosmetic fix. The affected section has to come down and the foundation be dug deeper to firm ground.
Mortar joints crumbling within a year
Cause: Mix too weak, or laid in frost — Fix: Rake out and repoint with a properly gauged mix in mild weather.
Questions people ask
How deep should the foundation be for a garden wall?
At least 300mm for a low wall on firm ground, and at least 450mm in exposed or frost-prone locations, always down to firm undisturbed subsoil. On clay, deeper — shrinkable clay moves seasonally near the surface.
What mortar mix should I use for a garden wall?
1:5 or 1:6 cement to building sand with a plasticiser for most modern bricks in normal exposure. Use a lime-based mix with older or softer bricks. Never go stronger than 1:4 outdoors.