How do I re-lay a sunken paving slab?

Lifting a slab without breaking it or its neighbours, finding out why it sank, and rebedding it so it stays level.

Difficulty
beginner
Time
1 hr 30 min
Read
4 min
Safety
caution

Short answer

Lever the slab out with a bolster and a bar, dig out the failed bed, and rebed it on a full mortar bed or five spots of mortar on a firm sub-base. Tap it down to the level of its neighbours with a rubber mallet and a straightedge across three slabs.

A slab sinks because what is under it has moved — a spot-bedded slab whose spots have failed, a sub-base that was never compacted, or water washing the bedding out. Rebedding on the same failed base just puts the problem back.

Safety

Paving slabs are heavy — a 600mm x 600mm concrete slab is around 40kg and a natural stone one considerably more. Lift with two people or use slab lifters, and never let a slab drop onto a foot. Wear gloves: freshly broken concrete edges are sharp.
A slab on a full mortar bed compared with five dabs

Step by step

  1. Work out why it sank before lifting it.One slab in the middle of a sound patio is usually a bedding failure. A run of slabs along a downpipe or a drain is water washing the bed away. A whole area sinking is a sub-base problem and needs more than one slab lifting.
  2. Free the joints.Rake or cut out the mortar or sand in the joints all round with a plugging chisel or an angle grinder. Levering against a jointed edge breaks the neighbouring slab.
  3. Lift the slab from one edge.Drive a bolster into the joint and lever gently, then get a bar underneath and work it up. Two people, or slab lifters, for anything over 450mm square.
  4. Clear out the old bed completely.Old mortar spots, wet sand, roots — all of it. Then check the base underneath. If you can push a screwdriver in easily, the sub-base needs attention too.
  5. Repair the base if it is soft.Dig out to firm ground, add MOT Type 1 in layers and compact each one. There is no point rebedding a slab on unstable ground.
  6. Bed on a full mortar bed.A 4:1 sharp sand to cement mix, semi-dry, spread to give 30-50mm of bed under the whole slab. A full bed is far more durable than five spots — spot bedding leaves voids that hold water and crack the slab.
  7. Level it against three neighbours.Lay the slab, tap down with a rubber mallet, and check with a straightedge spanning at least three slabs in two directions. Keep the fall of the patio consistent — the slab should not be flat if the patio falls.
  8. Leave it to set before jointing.24 hours before walking on it, then point the joints with a mortar mix or brush in a jointing compound. Keep the joint width consistent with the rest of the patio.
  9. Fix the water source if there was one.A slab that sank under a downpipe will sink again unless the water is taken away properly.

Tips

  • Number or photograph the slab before lifting if the paving is patterned or riven — putting it back the wrong way round is very visible.
  • A semi-dry mortar mix is easier to level a slab into than a wet one, and does not squeeze out into the joints.
  • If two or three adjacent slabs have sunk, lift them all and do the base properly. Doing them one at a time takes longer overall.

Common mistakes

  • Bedding on five spots of mortar — It leaves voids under the slab that fill with water, freeze, and crack the slab. It is also why the slab rocks when the spots fail. Use a full bed.
  • Levelling the slab flat rather than to the patio fall — A flat slab in a falling patio holds a puddle and looks wrong. Match the surrounding fall, using a straightedge across several slabs.

If it doesn't work

Slab rocks after rebedding

Cause: Voids in the bed, or bedded on too dry a mix that did not take up — Fix: Lift it, remake the bed with a full semi-dry mortar bed, and tap it fully down while the mortar is still workable.

Slab cracked while lifting

Cause: Levered against a jointed edge or an unsupported corner — Fix: Free every joint before levering, and lever from the middle of an edge. A cracked slab needs replacing — matching an old slab is the hard part.

Same slab sinks again within a year

Cause: Sub-base failure, not bedding failure — Fix: Lift, excavate to firm ground, and rebuild with compacted MOT Type 1 before rebedding.

New mortar joint a different colour

Cause: Different sand or cement from the original — Fix: Test a mix on a spare area first. Colour evens out over a year or two but never matches exactly.

Questions people ask

Can I just put sand under a sunken slab?

It will hold for a season and then sink again, because sand washes out. A full semi-dry mortar bed on a firm base is what keeps a slab level.

Why do slabs sink near a downpipe?

Concentrated water washes the bedding sand out from under the slabs. Fix the discharge first — a shoe into a gully, or a soakaway — or the paving will keep failing at that spot.

Written and maintained by the GuideHQ editorial team. More in Home & DIY.